Accessing the factors that affect the implementation of successful project management for TETFUND-sponsored projects in the South East, Nigeria (2011–2021)
1Ilo, Winnie Nneka; 2Nwagbara, Augustine and 3Nnadi, Ezekiel*
1Department of Project Management, ESUT Business School, Enugu
2Department of Architecture, Enugu State University of Science & Technology, Agbani
3Department of Civil Engineering, Kampala International University, Uganda.
*Corresponding author: Nnadi, E.O.E: nnadiezekiel@kiu.ac.ug
ABSTRACT
As important as the knowledge acquired via the teaching and learning process in tertiary institutions is the infrastructure in tertiary education. This is the case since infrastructure is one of the facilities that primarily supports the teaching and learning process. In Nigeria, tertiary education has faced and continues to face a number of difficulties throughout the years, one of which is the deterioration of the infrastructure necessary for professional and National University Commission (NUC) accreditation. The improper implementation of project management and the absence of integration of the services of the professional project manager in various TETFund Intervention Projects are two of the biggest difficulties experienced in the implementation of TETFund-Sponsored Projects. The upshot of this is that TETFund-Sponsored Projects have been delivered unsuccessfully. For this study project, the quantitative research method was used. For this study, official documentation of Annual Intervention Projects in 10 public recipient universities in South-East Nigeria was obtained. This study indicates that all the parameters indicated are drivers of successful project management with mean ratings over 2.5 based on the results it has received and assessed. The overall rating was 2.9, which is also higher than the benchmark norm. We reject the null hypothesis and come to the conclusion that there is no significant relationship between the variables of completed within time, not completed within time, completed but delayed, and not completed yet behind schedule. Hypothesis testing revealed that the value of the t-statistics (0.049) was below 0.05.
Keywords: Determinants, Implementation, Infrastructure, Project, Management.
INTRODUCTION
As important as the knowledge acquired via the teaching and learning process in tertiary institutions is the infrastructure in tertiary education. This is the case since infrastructure is one of the facilities that primarily supports the teaching and learning process. In Nigeria, tertiary education has faced and continues to face a number of difficulties throughout the years, one of which is the deterioration of the infrastructure necessary for professional and National University Commission (NUC) accreditation. The National Policy on Education [1] relates the relevance of higher education to the following: contributing to national development through training high level manpower; developing and inculcating proper values for the survival of the individual and society; developing the intellectual capability of individuals to understand and appreciate their local and external environments; acquiring both physical and intellectual skills which will enable individuals to be self-reliant and useful members of the society; promoting scholarship and community service; fostering national unity; and promoting national and international understanding and interaction. Overshooting the carrying capacity of most Nigerian Universities is foiling the realization of these objectives. [2], described carrying capacity as the maximum number of students that a university can sustain for quality education based on its human and material resources. Therefore, infrastructure is among the important operational inputs into any instructional programme. It constitutes elements that are necessary for teaching and learning; and is vital in the development of qualitative university education. [3], pointed out that the stress put on the universities in terms of demand and the limited expansion in physical facilities and academic staff to cater for this demand has taken a toll on the quality of programmes in the institutions. [4], thus submitted that the quality of output (graduates) is a function of infrastructure that determines the students’ learning environment and their motivation to learn. Implying that; if quality is to be assured in the nation’s universities, the infrastructural base of the system needs to be improved upon. Educational funds are opined to be disbursed for the general improvement of education in Federal and State Tertiary Education, and specifically for the provision or maintenance of essential physical infrastructure for teaching and learning among others [5].
TETFund projects like all other projects usually have both project inception and completion phases. Project phases encompasses: project design, project planning, project construction and project completion and handing over phases [6]. [7], asserts that no matter how small a project is, it has tendency of failure due to the inherent risks. Project Management on the other part is seen as the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. It involves defining project objectives, determining task required to complete it, decisions on important project milestone, determination of duration of project component tasks, planning for the most efficient organization of tasks and the allocation of resources to tasks [8]. Project management is believed to be justified as a means of avoiding the ills inherent in the construction and production sector of the economy and for which reasons most projects fail and or abandoned. The success of any project implementation process in the construction industry in the public and private sectors depends largely on the project manager’s concept of staff appointments and control, strict monitoring of time, cost, material, quality and environmental constraints. [9], asserts that project managers were not engaged at all in most of the projects in selected TETFund projects. Empirical evidence as stated by [10] proves that early engagement of project management techniques significantly improves project delivery success. The poor delivery, time and cost overrun ad lots of risks in the execution of TETFund project has brought to fore the emphasis on the need to employ a formidable project team with the project manager as the team leader, who will work harmoniously in the interest of the client to achieve project success as opined by [11]. It is imperative therefore to study the impact of implementation of project management on the successful delivery of TETFund-Sponsored projects with a view to proffering sustainable solutions to the problem of failed TETFund-Sponsored projects.
Aim and Objectives
The aim of this study is to determine the impact of the implementation of project management on the successful delivery of TETFund-Sponsored projects in South-East Nigeria from the purview of the project managers. The objectives are to examine the determinants of successful project management implementation of TETFUND sponsored project in public Universities and to determine the relationship between the variables of completed within time, not completed within time, completed but delayed, not completed yet behind schedule on the successful project management.
REVIEW OF RELATED LITERATURE
Implementation of project management practices is to achieve and enhance consistency in project success. It is also carried out to mitigate chains of risks that are synonymous to construction industry. It is imperative to look at project success as implantation of project within the budget, time frame, at expected quality with sustainable ends. It is not a gainsaying that the experience of the project manager influences the success of projects. [12], highlight that project management has its role in achieving project success, but several other factors beyond the control of project management, also affect project success. The concept of project success made [13] to opined that only the combination of project management success with product success will create project success, whereby [14] affirm that a project is only successful, when its objectives are achieved.
Project Management and its Impact on project Delivery
Project Management refers to the timely, routine and continuous monitoring, evaluation and implementation to actualize projects’ aim. The service of a project manager is unique and distinct. It uses a set of tools, techniques, principles and methods for planning and executing the project work effectively with the objective of completing the project in time, within the budget and according to the laid-down specifications [15]. According to Project Management Body of Knowledge [16], Project Management is seen as the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. It involves defining project objectives, determining task required to complete it, decisions on important project milestone, determination of duration of project component tasks, planning for the most efficient organization of tasks and the allocation of resources to tasks [17]. Project management is believed to be justified as a means of avoiding the risks inherent in the construction and production sector of the economy and for which reasons most projects fail and or abandoned. The project manager’s role arises from the need for a technical expert to take charge and control of events on the project implementation process; someone who understands the intricacies of co-coordinating, controlling, organizing and directing the efforts and activities of the professional team and the physical problems of implementation process with the needs in the decision-making process.
The success of any project implementation process in the construction industry in the public and private sectors depends largely on the project manager’s concept of staff appointments and control, strict monitoring of time, cost, material, quality and environmental constraints [17]. A good project manager is one who has been entrusted with the task of managing a specific project. An effective project manager is one who should have the following skills/capacities: Planning and organizational skills, personnel management skills, communication skills, change orientation, ability to solve problems in their totality, high energy levels, ambition for achievement, ability to take suggestion, understanding the views of project team members and having a sympathetic attitude towards them, ability to develop alternative actions quickly, knowledge of project management methods and tools, ability to make self-evaluation, effective time management, capacity to relate current events to the project/project management, integration skills, ability to handle project management software tools/packages, flair for sense of humour, solving issues/problems immediately without postponing them, initiative and risk taking ability, familiarity with the organization, tolerance for difference of opinion, delay, ambiguity, knowledge of technology, conflict resolving capacity, team building skills, resource allocation skills, entrepreneurial skills, and good skills of negotiation to gain the confidence and cooperation of many departments in the organization [15]. From the 2015 TETFund Guidelines for Accessing Intervention Funds it is clearly shown that no conscious effort was made by the Fund to incorporate the all-important role or professional expertise of the project manager to ensure successful project delivery. Also from observations, of projects accessed and executed from 2011 to 2021 by beneficiary institutions in South-East Nigeria, the services of the project manager are not being required by TETFund as a requisite professional expertise even when it is stipulated in the 1996 Federal Government Scale of Fees for remuneration of consultants in the construction industry.
Summary of Literature Review and Gaps
From the review of relevant literature; it was deduced that for TETFund Annual Intervention (Construction-related) Projects, the inputs of technical professionals in the construction industry are a major requirement for submission of project proposals by beneficiary institutions toward accessing intervention funds. However, from the guidelines, no conscious effort has been made by TETFund to include the right application of project management and the expertise of the professional project manager whose roles and duties cannot be overemphasized in ensuring successful project delivery in the construction industry. This study therefore seeks to examine TETFund-Sponsored projects in South-East Nigeria with a view to determining the extent to which project management elements and methods are applied in the implementation of the projects and its impacts on the successful delivery of the projects.
RESEARCH METHODOLOGY
This research aimed at collection data that would stand a position on the contributory roles of project management in the implementation of TETFund projects in South-East, Nigeria. For the purpose of this research, the area of study covers Public Tertiary Institutions, precisely Universities that are beneficiaries of the TETFund Annual Intervention Funds for Physical Infrastructural (Construction-related) Projects in South-East Nigeria. This study is quantitative research which adopts exploratory research design to achieve its objectives. However, exploratory research design is preferred in this study as the study interest is on revealing existing condition which are not obviously known. The researcher narrowed the sample observation to project managers, consultants and contractors that participated in TETFund projects in South-East between 2010-2021 which summed up to 675 respondents.
To get the sample size of the study, the researcher used Taro Yamane’s principles of arriving at a sample size which is given as
Where: n= Desired sample size
N= the entire population
e= level of significance or limit of tolerable error assumed to be 5% or 0.05
I= unit, constant figure
Table 1 Estimated Population Distribution and Sample Size of the Study
S/N | CATEGORIES OF RESPONDENTS | ESTIMATED POPULATION | SAMPLE SIZE |
1. | Contractor | 50 | 44 |
2. | Client/Project Managers | 45 | 40 |
3. | Consultants | 100 | 80 |
TOTAL | 195 | 164 |
Quantitative research design was adopted via a web-based designed and sent. Secondary data was extracted from documented records of projects accessed by beneficiary institutions as documented by TETFund from 2011 to 2021.
Table 2: TETFund Annual Intervention Projects for Physical Infrastructure in Universities in the South-East Nigeria from 2011-2021.
S/N | Name of Institution | No. of Projects from 2011-2021 | Projects Completed Within Schedule | Ongoing Projects, Still Within Schedule | Projects Not Yet Completed and behind Schedule | Projects Completed but not Within Schedule | ||||
Nos | % | Nos | % | Nos | % | Nos | % | |||
1 | ABSU | 8 | 0 | 0 | 0 | 0.00 | 5 | 62.50 | 3 | 37.50 |
2 | COOU, Anambra State | 3 | 0 | 0.00 | 0 | 0.00 | 3 | 100.00 | 0 | 0.00 |
3 | EBSU, Ebonyi State | 7 | 0 | 0.00 | 1 | 14.29 | 4 | 57.14 | 2 | 28.57 |
4 | ESUT, Enugu State | 10 | 0 | 0.00 | 2 | 20.00 | 2 | 20.00 | 6 | 60.00 |
5 | FUTO, Imo State. | 7 | 1 | 14.29 | 0 | 0.00 | 3 | 42.86 | 3 | 42.86 |
6 | FUNAI, Eboni State | 3 | 1 | 33.33 | 0 | 0.00 | 0 | 0.00 | 0 | 0.00 |
7 | IMSU, Imo State | 3 | 1 | 33.33 | 0 | 0.00 | 2 | 66.67 | 0 | 0.00 |
8 | MOUAU, Abia State | 3 | 0 | 0.00 | 1 | 33.33 | 0 | 0.00 | 2 | 66.67 |
9 | UNIZIK, Anambra State | 3 | 0 | 0.00 | 0 | 0.00 | 1 | 33.33 | 2 | 66.67 |
10 | UNN, Enugu State | 3 | 0 | 0.00 | 1 | 33.33 | 2 | 66.67 | 0 | 0.00 |
ANALYSIS AND DISCUSSION OF FINDINGS
The results of the data gathered to satisfy the first and second objectives were analyzed and shown in table 1 and table 2
Table 3: Examination of the determinants of successful project management implementation
S/N | The Project determinants | VGE | GE | LE | VLE | ∑FX | RESULT | |
1 | Project completed within time. | 45 | 50 | 23 | 17 | 135 | ||
180 | 150 | 46 | 17 | 393 | 2.9 | ACCEPT | ||
2 | Project not completed within time. | 50 | 49 | 30 | 6 | 135 | ||
200 | 147 | 60 | 6 | 413 | 3.0 | ACCEPT | ||
3 | Project completed but delayed. | 47 | 53 | 33 | 2 | 135 | ||
188 | 159 | 66 | 2 | 415 | 3.0 | ACCEPT | ||
4 | Project not completed yet behind schedule. | 40 | 55 | 30 | 10 | 135 | ||
160 | 165 | 60 | 10 | 395 | 2.9 | ACCEPT | ||
Grand total | 2.9 | ACCEPT |
Four questionnaire items were used to answer research question one. All the items had mean ratings above 2.5 The grand mean rating was 2.9 which is also above the criterion mean. Based on this, the researcher concludes that the listed items are the determinants of successful project management implementation of TETFUND sponsored project in public Universities.
Table 4: Determination of relationship between variables using Parsimonious Regression Result
Dependent Variable: D(SPM) | ||||
Method: Least Squares | ||||
Date: 07/16/23 Time: 09:40 | ||||
Sample (adjusted): 2011 2021 | ||||
Included observations: 37 after adjustments | ||||
Variable | Coefficient | Std. Error | t-Statistic | Prob. |
C | 0.027275 | 0.015832 | 1.722799 | 0.0949 |
D(PCWT) | 1.371105 | 1.192205 | 3.148861 | 0.0194 |
D(PNCWT) | -0.062995 | 0.053277 | -2.182397 | 0.0460 |
D(PCBD) | -0.000489 | 0.000157 | -3.103363 | 0.0041 |
D(PNCYD) | -0.014915 | 0.004793 | -3.111745 | 0.0040 |
R-squared | 0.632925 | Mean dependent var | 0.042191 | |
Adjusted R-squared | 0.525332 | S.D. dependent var | 0.041292 | |
S.E. of regression | 0.036343 | Akaike info criterion | -3.644225 | |
Sum squared resid | 0.040946 | Schwarz criterion | -3.382995 | |
Log likelihood | 73.41817 | Hannan-Quinn criter. | -3.552130 | |
F-statistic | 3.094308 | Durbin-Watson stat | 1.615606 | |
Prob(F-statistic) | 0.022223 | |||
Where,
SPM = Successful project management
PCWT = Project completed within time
PNCWT = Project not completed within time
PCBD = Project completed but delayed
PNCYD = Project not completed yet delayed.
Regression Result
In the regression result, the variables under consideration are successful project management (dependent variable), Project completed within time (PCWT), Project not completed within time (PNCWT), Project completed but delayed (PCBD), Project not completed yet delayed (PNCYD). From the result the estimated coefficient value of bo, b1, b2, b3 and b4 are 0.027275, 0.0000137, -0.062995, -0.000489, and -0.014915 respectively.
The regression equation is presented as follows:
SPM = 0.027275 + 0.0000137PCWTt – 0.062995PNCWTt – 0.000489PCBDt + 0.014915PNCYDt
Se = (0.015832) (0.0000119) (0.053277) (0.000157) (0.004793)
t* = 1.722799 1.148861 -1.182397 -3.103363 -3.111745
R2 = 0.332925
Adjusted R2 = 0.225332
F* = 3.094308
Durbin-Watson statistics = 1.615606
Evaluation of Regression Results
Evaluation Based on Economic Criterion
This subsection is concerned with evaluating the regression results based on a priority expectation. The signs and magnitude of each variable coefficient is evaluated against theoretical expectations. The constant term is 0.027275, which means that the model passes through the point 0.027275 mechanically. If the independent variables are zero, successful project management would be 0.027275, [18]. The estimated coefficient for project completed within time (PCWT) is 0.0000137. This implies that if all other variables affecting successful project management (SPM) are held constant, a unit increase in project completed within time will lead to 0.0000137 units increase in successful project management on the average. Similarly, the estimated coefficient of project not completed within time (PNCWT), Project completed but delayed (PCBD) and Project not completed yet delayed (PNCYD) are -0.062995, -0.000489 and -0.014915 respectively. This means that holding every other variables that affect successful project management (SPM) constant, a unit increase in Project not completed within time will bring about a 0.062995 units decrease in successful project management; a unit increase in Project completed but delayed will lead to a 0.000489 units decrease in successful project management, and a unit increase in project not completed yet delayed will bring about a 0.014915 units decrease in successful project management on the average.
Evaluation Based on Statistical Criterion
R2 –Result and Interpretation
This subsection applies the R2, the t-test and the f-test to determine the statistical reliability of the estimated parameters. These tests are performed as follows;
The coefficient of determinations, R2, from the regression result is given as 0.332925. This implies that 33.2925% of the variation in successful project management is being explained by the variations in Project completed within time, Project not completed within time, Project completed but delayed, Project not completed yet delayed.
T–Test Result and Interpretation
The study also employs the 95% confidence interval or 5% level of significance (i.e. =0.05) and df = n-K = 10-5 = 5 as the degrees of freedom.
From the distribution table, t0.025(34)= 2.042
The result of the t-test of significance is shown in table 4.5 below:
The result of the t-test is presented below and evaluated based on the critical value (2.042) and the value of calculated t-statistics for each variable.
Table 5: Result of T-Test of Significance
Variables | t-computed (t*) | t-tabulated (ta/2) | Conclusion |
PCWT | 3.148861 | 2.042 | Significant |
PNCWT | -2.182397 | 2.042 | Significant |
PCBD | -3.103363 | 2.042 | Significant |
PNCYD | 3.111745 | 2.042 | Significant |
Significant (Reject Ho; accept H1),
Insignificant (Accept Ho).
From the t-test result above, for PCWT, t*> ta/2, therefore, the null hypothesis is rejected. Hence, project completed within time is statistically significant, thus project completed within time has significant impact on successful project management. For PNCWT, t*> ta/2, therefore, the null hypothesis rejected. Hence, project not completed within time is statistically significant, thus project not completed within time has significant impact on successful project management. For PCBD, t*> ta/2, therefore, the null hypothesis rejected. Hence, project completed but delayed is statistically significant, thus project completed but delayed has significant impact on successful project management.
For PNCWT, t*> ta/2, therefore, the null hypothesis rejected. Hence, project not completed within time is statistically significant, thus project not completed yet delayed has significant impact on successful project management.
TEST OF HYPOTHESES
Table 6: one-sample test of the first hypotheses;
H0: there is no significant relationship between the variables of completed within time, not completed within time, completed but delayed, not completed yet behind schedule.
One-Sample Test | ||||||
Test Value = 0 | ||||||
T | df | Sig. (2-tailed) | Mean Difference | 95% Confidence Interval of the Difference | ||
Lower | Upper | |||||
there is no significant relationship between the variables of completed within time, not completed within time, completed but delayed, not completed yet behind | 0.049 | 10 | .014 | z17373.02000 | 16007.8096 | 18738.2304 |
From the test of hypothesis above using one sample test t-statistics, based on the decision rule, accept null hypothesis if the value of the t-statistics is greater than 0.05, from the result; the value of the t-statistics (0.049) is below 0.05 hence we reject the null hypothesis and conclude that there is no significant relationship between the variables of completed within time, not completed within time, completed but delayed, not completed yet behind schedule
CONCLUSION
From this result obtained and analyzed, this study concludes that the identified determinants of successful project management are project completed within time, project not completed within time, project completed but delayed and project not completed yet delayed. Further, the study also concludes that project completed within time has positive relationship on successful project management whereas project not completed within time, project completed but delayed and project not completed yet delayed have negative relationship on successful project management.
RECOMMENDATION
Based on the findings of the study, the following recommendations are given:
- All the determinants of successful project completion must be taken serious and attend to specifically
- Projects must be executed to budget, time and expected quality to make expected economic impact on the economy.
- There is need for careful monitoring the delivery of TETFUND in Nigerian Universities so as to avoid underutilization of public fund.
- Effective project management team should be encouraged in all TETFund projects to ensure value for money and continuity of the programme.
REFERENCES
- National Policy on Education in Nigeria (2004).
- Adedipe, N. O. (2007), University quality assurance, finding strategy and task allocation. Paper presented at the workshop on tertiary education financing. University of Lagos on April 23-24.
- Okebukola, P. (2002). The state of university education in Nigeria. Abuja: National University Commission.
- TETFund (2015). Guidelines for accessing TETFUND intervention funds. Abuja: TETFund.
- TETFund (2020). The Establishment and Mandate of Tertiary Education Trust Fund. tetfund.gov.ng, accessed on 7th January, 2001.
- Saidu, I. and Shakantu, W. (2016).The contributions of construction material waste to project cost overruns in Abuja, Nigeria’, Global Journal of Education Research, 13, pp. 63-72.
- Nnadi, E. and Ezemerihe, A. (2018). Value Management as an efficient risk management tool. International Journal of Advanced and Multidisciplinary Engineering Science.
- Nwachukwu, C.C. (2016), Dimensions of Real Estate Project Management.
- TETFund (2011). Guidelines for accessing TETFUND intervention funds. Abuja: TETFund.
- Kuprenas, J.A., Madjidi, F. and Smith, B. M. (2005). ‘Implementation of Project Management in Public Engineering Organization’, Journal of Construction Engineering and Management, 15(3), pp. 69-77.
- Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005). ‘Delays and cost increases in the construction of private residential projects in Kuwait’. Construction Management and Economics, 23(3), pp. 285-294. Doi: 10.1080/0144619042000326710.
- Munns and Bjeirmi (1996). The role of project management in achieving project success. International journal of project management.
- Baccarini, D. (1999). The logical framework method of defining project success. Project management journal.
- Lim and Mohamed (1999). Criteria of project success: An exploratory re-examination
- Nagarajan, (2012). Project Management (Sixth Edition). New Age International Publishers.
- PMBOK (2009). A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition.
- Akintoye, A. (2010). Major Challenges to the Successful Implementation and Practice of Programme Management in the Construction Environment: A Critical Analysis.
- Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005). ‘Delays and cost increases in the construction of private residential projects in Kuwait’. Construction Management and Economics, 23(3), pp. 285-294. Doi: 10.1080/0144619042000326710.
CITE AS: Ilo, Winnie Nneka; Nwagbara, Augustine and Nnadi, Ezekiel (2023). Accessing the factors that affect the implementation of successful project management for TETFUND-sponsored projects in the South East, Nigeria (2011–2021). NEWPORT INTERNATIONAL JOURNAL OF ENGINEERING AND PHYSICAL SCIENCES (NIJEP) 3(3):1-7. https://doi.org/10.59298/NIJEP/2023/10.1.1100
|